images/pol-pl.gif

List of projects

YEAR

PROJECT

TONNAGE (TONS)

2008

Rodsand B Trafoplatform

346,0

2008

Nini East – Deck 4

64,2

2008

Nini East A Platform

220,0

2008

Gunsfleet Sands
– Offshore Substation

580,0

2007

Horns rev. 2 – Foundation

81,1

2007

Robin Rigg substation –
Cable deck

250,0

2007

Robin Rigg Substation
– Equipment deck

135,0

2007

Upper Guide Arrangement for
Buoyancy Tank

169,5

2006

Lower Guide Arrangement for
Buoyancy Tank

72,0

2006

Q7 trafoplatform

250,0

2006

Lillgrund trafoplatform

300,0

2006

Texas Deck

130,0

2006

Supports for I-tubes

238,7

2006

Suction Anchors

124,0

2005

Top platforms for Near Shore

208,0

2003

Beacon Towers

701,2

2003

Platforms for Nini and Cecilie

52,7

2003

Seafastening for Nini and
Cecilie jacets

161,0

2003

Mudmads and saddles

144,0

2002

Seafastening for HDB and HDC

357,5

2002

4 seafastenings

100,0

2002

Ladders and boatlandings

33,0

2002

2 equipment rooms

89,0

2002

2 platforms for DONG

525,0

2002

Nysted Trafoplatform

288,0

2001

Nodes for DAN FF

49,7

Rødsand II Trafoplatform

Steel construction of this platform was delivered in 4 levels, each one delivered into smaller section and delivered for futher assembly to Bladt in Aalborg. The trafoplatform finally will gather electrcity from 90 wind turbines.

Parameters

Client: Energinet.dk
Start date:28/11/2008
End date:20/04/2009
Weight: 346 ton

Photo gallery

Gunfleet Sands Trafo Platforma

The trafoplatforms gathers electrycity from 48x3,6 MW wind turbines. The platform was fabricated in sections, assembled into decks on ship to Denamrk to Bladt where was finally merged. Expected time to start operation is in the begining of year 2010.

Parameters

Client: Dong Energy A/S
Start date:07/05/2008
End date:18/07/2008
Weight: 580 ton

Photo gallery

Lillgrund Trafoplatform

This is the first trafoplatform produced and delivered to Denmark in one element. After final instaltion on the sea, the trafoplatform gathers electrycity from 48 wind turbines.

Parameters

Client: Siemens Wind Power A/S
Start date:07/11/2006
End date:25/02/2007
Weight: 300 ton

Photo gallery

Q7 trafoplatform

Another substation produced and delivered in sections to Denmark. The trafoplatform for Q7 gathers electricity from 60 wind turbine.

Parameters

Client: Van Oord Dredging and Marine Contractors B.V.
Start date:15/11/2006
End date:18/02/2007
Weight: 250 ton

Photo gallery

Buoyancy tanks

Subassry produced in Poland for "Ballast tanks" used for disassembly of oil and gas platform.

Parameters

Client: Aker Kvaerner Offshore Partner A/S
Start date:22/08/2006
End date:19/12/2006
Weight: 500 ton

Photo gallery

Suction anchors

Suction anchors (Top Units) produced for offshore gas and oil platform.

Parameters

Start date:10/04/2006
End date:19/05/2006
Weight: 124 ton

Top platforms

36 external platforms produced by Polish subcontractor. They are part of seconadry steel structure for Wind Turbines foundation.

Parameters

Client: Balast Nedam
Start date:30/12/2005
End date:19/05/2006
Weight: 208 ton

Photo gallery

Nysted Trafoplatform

This is the first construction of the trafoplatform produced in sections by Polish Subcontractor. The elements were transported to Aalborg in Denmark, where Bladt assembled them into one unit. The substation after erection on the sea gathers electrycity from 72 wind turbines.

Parameters

Client: SEAS Distribution AmbA
Start date:29/05/2002
End date:14/11/2002
Weight: 288 ton

Photo gallery