List of projects
YEAR |
PROJECT |
TONNAGE (TONS) |
2008 |
Rodsand B Trafoplatform |
346,0 |
2008 |
Nini East – Deck 4 |
64,2 |
2008 |
Nini East A Platform |
220,0 |
2008 |
Gunsfleet Sands |
580,0 |
2007 |
Horns rev. 2 – Foundation |
81,1 |
2007 |
Robin Rigg substation – |
250,0 |
2007 |
Robin Rigg Substation |
135,0 |
2007 |
Upper Guide Arrangement for |
169,5 |
2006 |
Lower Guide Arrangement for |
72,0 |
2006 |
Q7 trafoplatform |
250,0 |
2006 |
Lillgrund trafoplatform |
300,0 |
2006 |
Texas Deck |
130,0 |
2006 |
Supports for I-tubes |
238,7 |
2006 |
Suction Anchors |
124,0 |
2005 |
Top platforms for Near Shore |
208,0 |
2003 |
Beacon Towers |
701,2 |
2003 |
Platforms for Nini and Cecilie |
52,7 |
2003 |
Seafastening for Nini and |
161,0 |
2003 |
Mudmads and saddles |
144,0 |
2002 |
Seafastening for HDB and HDC |
357,5 |
2002 |
4 seafastenings |
100,0 |
2002 |
Ladders and boatlandings |
33,0 |
2002 |
2 equipment rooms |
89,0 |
2002 |
2 platforms for DONG |
525,0 |
2002 |
Nysted Trafoplatform |
288,0 |
2001 |
Nodes for DAN FF |
49,7 |
Rødsand II Trafoplatform
Steel construction of this platform was delivered in 4 levels, each one delivered into smaller section and delivered for futher assembly to Bladt in Aalborg. The trafoplatform finally will gather electrcity from 90 wind turbines.
Parameters
Client: | Energinet.dk |
Start date: | 28/11/2008 |
End date: | 20/04/2009 |
Weight: | 346 ton |
Photo gallery
Gunfleet Sands Trafo Platforma
The trafoplatforms gathers electrycity from 48x3,6 MW wind turbines. The platform was fabricated in sections, assembled into decks on ship to Denamrk to Bladt where was finally merged. Expected time to start operation is in the begining of year 2010.
Parameters
Client: | Dong Energy A/S |
Start date: | 07/05/2008 |
End date: | 18/07/2008 |
Weight: | 580 ton |
Photo gallery
Lillgrund Trafoplatform
This is the first trafoplatform produced and delivered to Denmark in one element. After final instaltion on the sea, the trafoplatform gathers electrycity from 48 wind turbines.
Parameters
Client: | Siemens Wind Power A/S |
Start date: | 07/11/2006 |
End date: | 25/02/2007 |
Weight: | 300 ton |
Photo gallery
Q7 trafoplatform
Another substation produced and delivered in sections to Denmark. The trafoplatform for Q7 gathers electricity from 60 wind turbine.
Parameters
Client: | Van Oord Dredging and Marine Contractors B.V. |
Start date: | 15/11/2006 |
End date: | 18/02/2007 |
Weight: | 250 ton |
Photo gallery
Buoyancy tanks
Subassry produced in Poland for "Ballast tanks" used for disassembly of oil and gas platform.
Parameters
Client: | Aker Kvaerner Offshore Partner A/S |
Start date: | 22/08/2006 |
End date: | 19/12/2006 |
Weight: | 500 ton |
Photo gallery
Suction anchors
Suction anchors (Top Units) produced for offshore gas and oil platform.
Parameters
Start date: | 10/04/2006 |
End date: | 19/05/2006 |
Weight: | 124 ton |
Top platforms
36 external platforms produced by Polish subcontractor. They are part of seconadry steel structure for Wind Turbines foundation.
Parameters
Client: | Balast Nedam |
Start date: | 30/12/2005 |
End date: | 19/05/2006 |
Weight: | 208 ton |
Photo gallery
Nysted Trafoplatform
This is the first construction of the trafoplatform produced in sections by Polish Subcontractor. The elements were transported to Aalborg in Denmark, where Bladt assembled them into one unit. The substation after erection on the sea gathers electrycity from 72 wind turbines.
Parameters
Client: | SEAS Distribution AmbA |
Start date: | 29/05/2002 |
End date: | 14/11/2002 |
Weight: | 288 ton |